Description
Reports on a Carbon Capture and Storage (CCS) project to remove CO2 from the process gas streams of the three hydrogen-manufacturing units which are a part of the Scotford Upgrader infrastructure. The Scotford Upgrader is owned by the Athabasca Oil Sands Project, a joint venture operated by Shell and owned by Shell, Chevron Canada Corporation, and Marathon Oil Sands LP. The Upgrader is part of Shell’s Scotford facility located northeast of Edmonton.
Updated
March 1, 2014
Tags
Resources
-
Quest Carbon Capture and Storage project : annual summary report - Alberta Department of Energy : 2013
Downloads: 576
-
Environmental screening report for the Shell Canada Ltd. Quest Carbon Capture and Storage project
Downloads: 143
-
Annex 2 : Shell Quest CCS project environmental assessment commitments
Downloads: 111
-
Quest project WBS procedure
Downloads: 174
-
Project execution plan
Downloads: 185
-
Project control plan
Downloads: 138
-
Second annual status report to AER. Part 1
Downloads: 194
-
Second annual status report to AER. Part 2
Downloads: 134
-
Second annual status report to AER. Part 3
Downloads: 132
-
Measurement, monitoring and verification plan : update
Downloads: 216
-
Closure plan - 3rd year update
Downloads: 115
-
2013 stakeholder engagement
Downloads: 79
-
General arrangement drawings / plot plans – final
Downloads: 285
-
Hydrogen manufacturing unit : overall plot plan
Downloads: 184
-
Hydrogen manufacturing unit : utility station location plan
Downloads: 110
-
Line break valve #1 site : plot plan
Downloads: 157
-
Module drawing key plan : Unit 285
Downloads: 138
-
Piping and instrument diagram : PIG launcher
Downloads: 219
-
Piping and instrument diagram : Unit 241
Downloads: 194
-
Piping and instrument diagram : Unit 242
Downloads: 149
-
Piping and instrument diagram : Unit 246 part 1
Downloads: 179
-
Piping and instrument diagram : Unit 246 part 2
Downloads: 141
-
Piping and instrument diagram : Unit 247 - compression - CO2 compressor 1st stage
Downloads: 214
-
Piping and instrument diagram : Unit 248 - dehydration
Downloads: 150
-
Piping and instrument diagram : Unit 440
Downloads: 135
-
Piping and instrument diagram : Unit 441
Downloads: 117
-
Piping and instrument diagram : wellsite #1 filtration and control
Downloads: 145
-
Piping and instrument diagram : wellsite #1 lateral pipeline
Downloads: 150
-
Piping and instrument flow diagram : fire water system
Downloads: 110
-
Piping and instrument flow diagram : unit 250
Downloads: 123
-
Piping and instrumentation diagram : hydrogen manufacturing unit : flare
Downloads: 117
-
Process flow diagram : hydrogen manufacturing unit
Downloads: 193
-
Unit 485 plot plan
Downloads: 137
-
Utility flow diagram
Downloads: 164
-
Wellsite plot plans
Downloads: 206
Title and publication information
Type
Frequency
Annual
Publisher / Creator Information
Creator
Publisher
Energy
Contributor
Contributor
Contributor
Subject Information
Topic
Resource Dates
Date Created
2014-03-01
Date Added
2019-02-04T18:16:27.614552
Date Modified
2014-03-01
Date Issued
2014-03-01
Audience information
Language
Identifiers
Usage / Licence
Usage Considerations
These reports, and the data and information contained in the reports, are provided to the Government of Alberta by Shell Canada Energy, Chevron Canada Ltd. and Marathon Oil Canada Corporation, and the Government of Alberta has obtained a license or other authorization for use of the reports. The Government of Alberta’s intent in posting the reports is to make them available to the public for personal and non-commercial (educational) use. They are not meant to be used for any other purpose. Please see the full disclaimer and terms and conditions of use appended to the beginning of each report in this record.